High Contrast Mode:

a wooden bridge over a river

Case Study

Big Creek - Roswell, GA

Situation

Two raised pedestrian walkways along the Big Creek Trail in Roswell, GA, were experiencing frequent flooding and silt buildup, creating hazardous conditions for trail users. The city needed a reliable solution to prevent further erosion and ensure safety.

Scope of Work

Cantsink was engaged by the general contractor to provide a solution. After assessing the existing conditions, it was determined that the original piles could not be extended due to uncertainty around their capacity. The project involved removing the existing decking and piles, and installing new piles at the correct elevations, with timber brackets, new joists, and decking to prevent future flooding.

Anchor System

Cantsink installed 10"/12" double helix helical piles with galvanized 2.875 o.d. configuration using an Eskridge 5500 drive head. A pattern of three piles per bent (two outer and one alternating center battered pile) was followed, with 13 piles in the first section and 45 in the second. Average pile depths were 21 feet in Section 1 and 34 feet in Section 2.

Result

The height of the walkways was raised by approximately one foot, eliminating flooding. The new piles were successfully installed, and decking was placed on the timber brackets. The City of Roswell was satisfied with the results, and the local community can now safely enjoy the trail.

Download PDF